Next Round of Public Open Houses this Month
The project team will return to Marshall and St. Joseph counties April 15 and 16 to discuss design and construction plans and answer questions from residents. Meeting times and locations are:
Wednesday, April 15
4 to 7 p.m.
LaVille Jr.-Sr. High School
69969 US 31 South
Lakeville, IN 46526
Thursday, April 16
4 to 7 p.m.
Jackson Intermediate Center
5001 S. Miami Rd.
South Bend, IN 46614
The project team will have design and construction plans available for residents to review. Land acquisition specialists also will be there to answer questions about land purchasing and relocation.
Updated maps presented at the open houses will be loaded on the project Web site. Visit www.us31plysb.com and click on “Maps” to access them.
Lilac/Tyler Road Contract Awarded, Construction to Begin
The contract to construct the Lilac/Tyler Road bridge over US 31 has been awarded to Primco, Inc., the same contractor performing the grading work, for $2.27 million. Construction is scheduled to begin in approximately six weeks and will be complete in fall 2009.
Check the “Construction/Closure Info” button on the Web site for up-to-date information about the road closures.